Once initial plans were finalised the build got underway, starting with the demolition and removal of the clubs' existing seating facility.
After the removal the ground was prepared for the third phase construction of the steelwork stand.
The structural steel is supported on 120 steel piles driven to a depth of 22m and encased in concrete, attached to the piles is the stand frame with 7m legs to the rear and 14m legs at the front (Initial designs had included plans without front support legs but time constraints prohibited the additional work needed).
The stand was erected in 3 weeks, with cladding to the roof and rear elevation.